Limited Viable Grid Connections Challenge Renewable Energy Sector

July 2025

Grid Reform is continuing to challenge the renewable energy sector with new viable grid connections becoming increasingly scarce. The changes have created some opportunities though with smaller projects under 5MW now being exempt from requiring a Transmission Impact Assessment (TIA). This has simplified the grid application process for sites under 5MW which should allow projects to connect sooner benefitting both developers and landowners.

However, a big health warning should come with this before developers seek to develop anywhere in the country. Some grid supply points (GSPs) are exempt from this fast-track process and therefore it is well worth dealing with grid consultants on this point before site finding is engaged.

At HK&Co we are working with a number of developers that are exploring these opportunities, looking for sites around 15 – 20 acres that are near suitable substations for the project to connect.

For more information, please take a look at the National Energy System Operator Website

Limited Viable Grid Connections Challenge Renewable Energy Sector

July 2025

Keep up to date with the latest developments in commercial property and our land development projects.

Name(Required)
I am interested in

By subscribing to this newsletter you are agreeing to be added to our mailing list. You can unsubscribe at any time.